|
Introduction to Surface Mining/Open
Pit Mining
Lesson 7
Objectives:
1)Students will describe how the ground's
water pressure effects the stability of the layout of the open
pit mine.
2)Students will explain how economics of
the mine are determined by design, available equipment, and mining
ratios to production ratios.
Metaliferous deposits that occur near the
surface are mined by open pit methods. Quarrying and strip mining
methods are used for other deposits such as sand, gravel, iron
ore and coal. The advantages of open-pit mining over underground
mining are lower costs, greater safety, and mechanically easier
operations. These open pit mines range in sizes from "dog
holes" to one half cubic mile. Many low-grade deposits are
mined this way because of the lower costs and higher productivity.
Soil and barren rock must be removed to expose the ore bodies.
This process is known as pre-production stripping. This process
of stripping this surface away may take a short time or as long
as years. A series of benches that are arranged in spiral or
connecting ramps are developed. The ramps or benches are usually
25ft to 100ft wide, with heights being 25 to 70 feet. Equipment
and stability of the rock determine the height and width of the
each bench. Bench height and width
are also related to slope stability. The slope can vary
between 20% to 70%, with the limit being determined by slope
stability and economics.
The amount of barren rock that is to be mined is the major consideration
in open-pit mining planning.
Open Pit Mining
The basic concept of an open pit mine
is simple. Open pit mines, however, require a lot of planning
to make sure that as much ore as possible can be extracted. Note:
the problems and cost of removing overburden often dictate the
limits of the pit.
Mining is done at large pits by track-mounted
electric shovels. Diesel-powered front end loaders are generally
used at smaller operations. Truck, railroad, or conveyors usually
do haulage.
Open Pit Mine- an excavation or
cut made at the surface of the ground for the purpose of extracting
ore and which is open to the surface for the duration of the
mine's life. To expose or mine the ore, it is generally necessary
to move large quantities of waste rock. The purpose of the mine
is to make a profit so careful planning and engineering must
take place from the very beginning. The planning of an open pit
mine is an exercise in economics, constrained by geologic, and
mining engineering aspects.
Increased population, created greater demand,
which in turn, initiated increased productivity. Production increased
with improved engineering and technology and for the most part,
greater productivity by workers. The shift was from underground
mining to surface mining even though the grade and quality was
declining.
It is generally conceded that surface mining
is more advantageous than underground mining in terms of recovery,
grade control, economy, and flexibility of operation, safety,
and the working environment. There are many deposits, that are
too small or irregular, and or deeply buried to be extracted
economically by surface mining methods. When the minerals extend
deep in the ground, the removal of the waste rock becomes too
cumbersome and expensive and the mine must be converted to underground
operations or abandoned.
Open pit design is conducted in several
stages.
Devising a scheme or set of
alternatives
Evaluation
Selection of optimum scheme |
The most economic final pit design is often
out of the hands of the designer. The design depends of factors
such as:
Geometric outline of the ore
body,
The topography
Maximum allowable slope angles |
In the end, the economics depend on the engineers' choice of
plans, equipment and the mining ratio to production rates.
Exploration Input for Open Pit Planning
The data from the core samples
is crucial at this point. Besides the information collected thus
far being used to determine the shape and size of the ore body,
these core samples help determine the slope stability. The water
pressure plays and an important role in the stability of the
slope also.
The detrimental effects of the presence of ground water on surface
mining are:
Water pressure
reduces the stability of the slope and tends to induce sliding
of materials in the slope
Increased weight of the unit rock thus higher rates for transportation.
Freezing water can block drainage paths
Erosion can cause instability and silting up of drainage systems
Increased operating costs from discharge of water for equipment
and blasting costs |
Bench Plan Preparations
Technology plays an important role in planning and the design
of a modern mine operation. A model representation is created
called a block model or ore body model. The models enable mining
planners to effectively select the most promising means of extracting
the ore body both physically and economically. With the assistance
of modern computer facilities, sophisticated and complex bench
plans can be prepared.
Stripping Ratio Considerations
The term stripping ratio
is almost universally used and represents the amount of uneconomic
materials that must be removed to uncover one unit of ore. The
ratio of total volume of waste to ore volume is defined as the
overall stripping ratio.
R=volume of waste removed to depth d = ABD
____________________________________________
Volume of ore recovered to depth d = BCED
While a volume relationship, calculated
in cubic yards/cubic yards (cubic meters/cubic meter). It is
more commonly expressed as tons/tons. Note that in mining certain
mineral commodities, however, stripping ratio is expressed
in units of cubic yards/ton.
Cutoff stripping ratio is the one that the costs of mining the ore and
waste are matched by the revenue for that block of ore. Factors
used to determine costs should include the added costs of mining
as the mine deepens and the interest charges on the prestripping
of waste.
In the most complete analysis, the entire
ore body is mined on paper. The production from each time period
is determined, the costs and revenues listed, and a cash flow
generated. The profits are projected. The result is to be the
value of the mine or production. Mining is continued until it
no longer increases the value, and so a pit limit is determined.
The ratio of the total volume of waste to total volume of ore
is then the overall stripping ratio,
Mining Plan Options
Declining Stripping Ratio Method-
this requires that each bench of ore be mined in sequence, and
all the waste on the particular bench is removed to the pit limit.
| Advantages |
Disadvantages |
1. Operating space available
2. Accessibility of the ore on subsequent bench
3. All equipment working on the same level
4. No contamination form waste blasting above the ore
5. Equipment requirements are minimum towards the end of the
mine's life |
1. Operating costs are
a maximum during initial years when profits are required to handle
interest and repayment of capital. |
Increasing Stripping Ratio Method- stripping is performed as needed to uncover the
ore. The working slopes of the waste faces are essentially maintained
parallel to the overall pit slope angle.
| Advantages |
Disadvantages |
1. Maximum profit in the initial
years
2. Greatly reduces investment risks in waste removal for ore
to be mined at future date
3. Method is popular where the mining economics or cutoff ratio
is likely to change |
1. Impracticality of operating
a large number of stacked, narrow benches simultaneously to meet
production needs. |
Constant Stripping Ratio- This method attempts to remove the waste at a
rate approximated by the overall stripping ratio. The working
slope of the waste face starts very shallow, but increases as
mining depth increases until the working slope equals the overall
pit slope.
| Advantages |
Disadvantages |
1. Equipment fleet size and labor
requirements throughout the project are relatively constant.
2. Good profit initially to increase cash flow.
3. Distinct mining and stripping areas can be operated simultaneously,
allowing for flexibility in planning. |
1. Disadvantage and advantages is the compromise
that removes the extreme conditions of other two stripping methods.
|
Mine Plan Frequency- Mine plans vary in frequency from short to long
range. The plans can be daily, weekly, monthly, yearly or a life-of-the
mine plan. The shorter the plan the more concise it will need
to be. The longer plans will have to establish financial forecasts
for replacement of equipment, variations in operating costs due
to haul distances, and dewatering requirements. Changes in the
ore type may dictate plan changes also.
Feasibility Studies- Once the mineral deposit has been discovered and
evaluated thoroughly enough to be considered an ore body, the
next problem is how to mine the ore that will maximize the the
net present value (NPV). The plan must figure in the best way
to get the most from the mine early in the operation to cover
high interest and to improve cash flow. The best ore grade may
be removed first to increase finances or the early plan may include
beginning to operate in a low waste-to-ore ratio area of mine
site.
(Littleton, Colorado: Society for
Mining, Metallurgy, and Exploration, Inc., 1992), pp. 1274-1278.
Vocabulary:
Open
Pit Mine- an excavation or cut
made at the surface of the ground for the purpose of extracting
ore which is open to the surface for the duration of the mine's
life.
Bench-a ledge that forms a single level of operation
above which mineral or waste materials are mined back to a bench
face.
Bench
height-vertical distance between
the highest point (crest) of a bench and the lowest (toe) of
the bench.
Bench
slope- the angle, measured in degrees
between the horizontal and an imaginary line joining the crest
and the toe of the bench.
Pit limits- the vertical and lateral extent to which the
open pit mine may be economically conducted.
Berm- a horizontal shelf within the pit wall slope
that is left for stability. The berm slope angle and width are
determined geotechnical configuration.
Haul road- a road is maintained in a uniform spiral arrangement
from top to bottom of the pit. A zigzag or switch back haul road
system is dependent upon the shape and size of the ore body and
equipment and the stability of the pit.
Angle
of repose- is the maximum slope
at which a heap of loose material will stand without sliding.
Suboutcrop
depth- is the depth of the waste
that has to be removed before ore is exposed.
Surface
Mining- Metaliferous deposits that
occur near the surface are mined by open pit methods. Quarrying
and strip mining methods are used for other desposits such as
sand, gravel, iron ore and coal. The advantages of open-pit mining
over underground mining are lower costs, greater safety, and
mechanically easier operations. These open pit mines range in
sizes from "dog holes" to one half cubic mile. Many
low-grade deposits are mined this way because of the the lower
costs and higher productivity.
Soil and barren rock must be removed to expose the ore bodies.
This process is known as pre-production stripping. This process
of stripping this surface away may take a short time or as long
as years. A series of benches that are arranged in spiral or
connecting ramps are developed. The ramps or benches are usually
25ft to 100ft wide, with heights being 25 to 70 feet. Equipment
and stability of the rock determine the height and width of the
each bench. Bench height and width are also related to slope
stability. The slope can vary between 20% to 70% with the
limit being determined slope stability and economics.
The amount of barren rock that is to be mined is the major consideration
in open-pit mining planning.
References:
**This article was adapted from
G.A. Fourie and Gerald C Hohm, JR. SME Mining Engineering
Handbook, 2nd Edition, Volume 2. (Littleton, Colorado:
Society for Mining, Metallurgy, and Exploration, Inc., 1992),
pp. 1274-1278.
Delta Mine Training Center
Copyright © 2001 DMTC. All rights reserved.
|