 Underground Mining
Lesson 10-Task

Microsoft Word Document Task/ Quiz 10Download this to have this assignment in a Microsoft Word Document that you can edit.


1. In your own words, summarize the four steps the mine planning process goes through.

2. Go to http://www.pogomineeis.com/baseline.htm

In the Pogo Mine Baseline, Section 2 OPERATIONAL REQUIREMENTS

A.Pogo Mine will be mined in a proven method called _______________.

In your own words, explain this method.

B. How do they plan to deliver fresh air to POGO mine?

C. Reading the Pogo Mine flow chart, what colors are the water and slurry ?

d. At the Pogo mine, the water supply that is primarily used for slurry preparation comes from four sources. Name three.

MOVE THIS TO CHAPTER 12 ENVIRONMENTAL 3.In this lesson it was found that the planning process requires at least a minimum of baseline of environmental data.

1) overburden analysis

2) soil surveys identifying topsoil and subsoil

3) hydrolic studies

4) determination of characteristics of surface and ground water

5) vegetation and existing land use surveys

6) air quality analyses

7) wildlife surveys

8) archeological surveys

 

How does the POGO baseline data plan to meet the above requirements? Pick 5 and discuss.

http://www.pogomineeis.com/baseline.htm

These are very large PDF files and may take some time to download. Some documents are 176 pages long. This is a good resource as it is recent and is utilizing current regulations.

 

 

 

 